• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Electric Power Supply Association

  • Insights
  • Podcast
  • About EPSA
    • Policy Principles
    • EPSA Members
    • Our Staff
    • Careers
  • For Members
    • Join EPSA
    • Committees
  • Contact
  • FAQ
EPSA

EPSA

  • Newsroom
    • Media Contacts
    • Press Releases
    • PowerFacts
    • Factsheets and White Papers
    • Power Moves Newsletter
    • Opinion and Commentary
    • Social Media
    • Podcast
  • Policy & Advocacy
    • Policy Positions
    • Federal Energy Regulatory Commission
    • Federal
    • Judiciary
    • State
    • ISOs/RTOs
  • Power Facts
    • Rising Power Demand
    • Reliable Power
    • Energy Cost Savings
    • Environmental Progress
    • Energy Innovation
    • In Your State
  • Understanding Your Electric Bill
Home / PowerFacts / EPSA Explores: Co-Location and Data Centers

November 13, 2024

EPSA Explores: Co-Location and Data Centers

By EPSA

Our electric grid faces an uncertain future, with challenges stemming from rising demand and rapid retirements of critical resources exacerbated by aspirational policies that frequently race ahead of operational and engineering realities.  

In the final installment of our three-part series on how to power the economy of the future, in which EPSA is offering perspective on the most important energy policy issues yet to be addressed and potential for progress, we’re delving into new proposals to co-locate large energy users like data centers with power generation resources. 

EPSA has developed its own Co-Location Principles to inform the development of new regulations and policies for competitive power markets. These principles can help the U.S. meet new demand cost-effectively, efficiently, and rapidly – while ensuring that investors, not customers, bear the risks of this shift.  

Read EPSA Explores: What Needs to Happen to Power the Economy of the Future – Part One: Consistent Price Signals  

Demand Growth Spurs Creative Solutions

Graph depicts the Goldman Sachs estimate for U.S. and global energy demand growth from 2014-2030 driven by artificial intelligence. Source: Goldman Sachs 

Data centers have emerged as one of the biggest drivers of electric load growth across the country. Driven by the artificial intelligence (AI) boom, estimates for future demand are rising. After remaining flat for decades, U.S. power demand is set to increase 2.4 percent by 2030, with nearly half of that due to data center demand. McKinsey now expects data centers to demand more than 50 gigawatts (GW) by 2030. That’s more electricity than the state of Pennsylvania currently produces.  

Energy leaders in Congress are already working to see how the U.S. can best address this projected load growth. But with a burdensome legislative and regulatory landscape slowing new build of energy resources, companies are already exploring other ways to address concerns.  

“Co-location” is one of these tools. It’s a simple concept with a long history: build large industrial facilities that demand significant power on or near the site of a power plant. This concept dates back to some of the first large generation facilities in the U.S., when major energy-intensive industries like aluminum processing were built alongside hydropower dams.  

Now, with proposed data centers demanding hundreds of megawatts on a constant basis, many of them are looking to buy power directly from a generator instead of connecting to their local utility. To meet the tech sector’s demand for 24/7 electricity from clean sources, the ideal generation source is often nuclear.   

Reliability and Cost Concerns to Be Addressed

The crux of the debate is whether co-location will remove too much power supply from the grid to service data centers or increase costs. Representatives Cathy McMorris Rodgers (R-WA), Chair of the House Energy and Commerce Committee, and Jeff Duncan (R-SC), Chair of the House Subcommittee on Energy, Climate and Grid Security, described their own hesitancies around co-location in a letter to the FERC commissioners:  

“[T]here is a powerful financial incentive for data centers to enter into power purchase agreements with thermal generators “behind-the-meter,” which risks taking reliable sources of generation out of the market and depriving grid operators and ratepayers of important sources of reliable generation.” 

However, the Nuclear Energy Institute (NEI) in a recent research paper, found that: 

“Like any grid-connected generator, the co-located generator will continue to deliver any generation not consumed by the data center onto the grid for the benefit of the network’s customers. Reducing the output of these generators has no material bearing on the system or its costs.” 

These concerns are particularly acute as ambitious climate policies at the state and federal levels continue to push reliable, dispatchable resources like coal and gas to retire. But behind-the-meter deals like these could also be a solution, by sending strong market signals that would encourage more investment in building new, dispatchable resources. 

Deals like these are one way to take advantage of the benefits of market structures—shifting risks and costs for new generation to large companies and investors rather than everyday households. If done right, they could allow development of new generation resources to happen faster and in a way that shifts costs away from consumers. 

FERC Weighs In

Now the issue has fallen to the Federal Energy Regulatory Commission (FERC) to help decide. The FERC Commissioners hosted a technical conference on November 1 to examine the issues and possible ways to resolve the competing interests. At the conference, the issue of co-location was framed as part of a larger issue about meeting growing energy demand amid retirements, supply chain challenges, and long permitting delays.  

Regulators, grid operators, and industry representatives including competitive power generators and tech companies identified issues to address, including:  

(1) the need for transparency and ensuring accurate load forecasts to facilitate planning for generation and transmission infrastructure to serve growing data center demand;  

(2) ensuring there are adequate generation resources to serve both existing retail electricity customers and the expanding energy needs of data centers;  

(3) updating market rules to ensure that customers, including data centers, pay for the grid services that are necessary to deliver their electricity, and that there are appropriate market mechanisms to incent generation facilities to come online when needed and stay online in the long term;  

(4) further reforms to transmission planning and interconnection processes to more quickly and efficiently add new generation to the grid; 

(5) clarifying state and federal jurisdictional responsibilities; and  

(6) ensuring regulatory tools are available to state and federal regulators as they monitor and oversee grid expansion, including policy modifications that may be needed to address data center expansion.  

After the technical conference, Todd Snitchler, president and CEO of EPSA said in a statement: 

“We are pleased to see FERC’s leadership on this issue and believe today’s constructive and enlightening discussions will help provide opportunities to flesh out the optimal outcomes for consumers and a reliable power system…[As] with any new arrangement that could impact the existing grid and competitive markets, getting the particulars right and carefully assessing surrounding market ramifications is essential.” 

After the conference, FERC blocked an Amazon-Talen Energy “behind-the-meter” deal to increase by an additional 180 MW – from the already approved 300 MW – the electricity supplied directly from the Susquehanna nuclear facility to an Amazon data center, finding that the legal requirement for the requested deviation from the standard agreement had not been met. The Commission therefore declined to address policy issues raised by parties in this individual proceeding. 

The decision comes after FERC issued a letter to PJM Interconnection requesting additional information—especially around reliability. In his dissent, FERC Chairman Willie Phillips argued that PJM did address reliability and that the order was a “step backward” for grid reliability. Commissioner Christie concurred on the decision emphasizing that the filing was rejected without prejudice. He highlighted that this type of co-location arrangement presents “an array of complicated, nuanced and multifaceted issues” which collectively could have significant ramifications for both grid reliability and consumer costs – and accordingly, the Commission needs to “get it right” when evaluating co-location issues. 


The Bottom Line

As the voice of competitive power providers, EPSA remains dedicated to exploring all solutions that can help the U.S. meet its growing power needs through competitive, market-based solutions that encourage investment and innovation. Markets have consistently proven themselves to be the best tool to ensure cost-effective, clean, and reliable energy without burdening customers with more non-bypassable charges on their bill.  

While questions remain about how co-location can help meet the moment and the role it can play in delivering technological advancement, EPSA believes that these arrangements are a promising solution to meet growing specialized demand.  

EPSA supports innovative solutions to market challenges that prioritize competition, open access, and innovation while ensuring a reliable and cost-effective energy system that puts investment risks on companies, not captive customers.  

Learn more about EPSA’s Co-Location Principles here. 


More in this Series

The missing pieces may be falling into place to meet the needs of the future. Increasingly realistic rhetoric and policies and new reforms are showing that the right things in energy policy are finally happening. However, there’s a long way to go before customers can be assured the electric grid can meet long-term needs reliably through competitive markets that function well.    

More remains to be done, but there is a growing sense that a viable roadmap exists. In this three-part EPSA Explores blog series, EPSA offers its perspective on the most important issues that still need to be addressed—and the signs we’re seeing today that demonstrate progress.   

EPSA Explores: Permitting and Interconnection Reform

By creating predictability around the regulatory process, permitting reform would dramatically improve the efficiency of building new projects and ensure that the U.S. maintains a reliable, clean, and cost-effective energy system capable of meeting new demand.  

EPSA Explores: Consistent Price Signals

“A well-functioning market balances supply and demand. But a mixture of out-of-market subsidies and increasingly disruptive market operations has kept prices artificially low. Now, companies are beginning to see the price signals they need to invest and be compensated for the risks involved.”  

Filed Under: Homepage Featured Article, PowerFacts Tagged With: 2024, AI, capacity, Co-location, colocation, Data Centers, Electric Power Supply Association, EPSA, epsa blog, EPSA Explores, EPSA news, load growth, rising demand

Primary Sidebar

  • Media Contacts
  • Press Releases
  • Power Moves Newsletter
  • Factsheets and White Papers
  • Opinion and Commentary
  • Social Media
  • Podcast

Share

Home Page Help Area

Sign up for EPSA’s Power Moves newsletter – a monthly update on the road to a reliable energy future that works for all Americans.

LEARN MORE

Footer

1401 New York Ave. NW
Suite 950
Washington, DC 20005

p 202.628.8200
f 202.628.8260

  • Facebook
  • LinkedIn
  • Twitter
  • Home
  • About EPSA
  • Filings
  • Newsroom
  • For Members
  • Contact
  • PowerFacts
  • FAQ

Copyright © 2026