EPSA and P3 urge FERC to reject Exelon utilities’ petition seeking overly broad declarations on co-located generation and end-use load issues.
Date filed: October 30, 2024
Venue: Federal Energy Regulatory Commission (FERC)
Docket No.: EL24-149
Co-location remains a new and innovative approach to serving certain large end-use customers, with a wide range of emerging potential structures and business relationships. Blocking competitive supply options for large energy users like data centers stymies economic development.
On October 30, 2024, the Electric Power Supply Association (EPSA) and the PJM Power Providers Group (P3) filed a joint protest at the Federal Energy Regulatory Commission (Commission) in response to the Exelon utilities (Baltimore Gas and Electric and PECO Energy Company) Petition for Declaratory Order (Petition) on co-location issues.
The EPSA and P3 protest calls for rejection of the Exelon Petition because the declarations requested are overly broad and ignore that there may be an array of contractual and operational structures utilized by co-located generation and end-use load.
EPSA and P3 explain that while the jurisdictional and interconnection agreement issues are described in the Petition as simple and clear, co-location remains a new and innovative approach to serving certain large end-use customers, with a wide range of emerging potential structures and business relationships.
This range of possible co-location structures and arrangements is the focus of the Commissioner-led technical conference, Large Loads Co-Located at Generating Facilities, held on November 1, 2024. Accordingly, EPSA and P3 emphasize that the Commission should not skip ahead of that discussion to make generic declarations without a specific contract, arrangement, or configuration to be assessed.
EPSA previously noted that Exelon’s requested revisions would impose barriers to competitive power supply options for large energy users like data centers and stymie economic development at a time of increasing need for energy infrastructure.