EPSA acknowledged MISO’s improvements to the ERAS proposal, but additional adjustments are necessary to prevent undue discrimination and ensure open access.
Date filed: June 16, 2025
Venue: Federal Energy Regulatory Commission
Docket No.: EL25-2454-000
On June 16, 2025, the Electric Power Supply Association (EPSA) submitted comments to the Federal Energy Regulatory Commission (FERC) on the Midcontinent Independent System Operator’s (MISO) revised proposal to implement an Expedited Resource Addition Study (ERAS) process. While EPSA acknowledged that MISO’s revised plan includes welcome improvements, especially the inclusion of independent power producers (IPPs), the Association raised serious concerns about the proposal’s clarity, fairness, and alignment with open access principles.
Key Issues Highlighted by EPSA
- Insufficient Transparency and Objectivity: EPSA noted that MISO’s proposal still fails to meet the basic threshold of “objective and transparent” standards for project prioritization. Unlike other ISOs, such as CAISO, MISO does not require regulators to publish or justify criteria for selecting ERAS projects. EPSA warned that without clear metrics or comparative processes, the ERAS program risks arbitrary outcomes and could unfairly disadvantage certain market participants.
- Discriminatory Barriers for Independent Power Producers: While MISO has carved out ten ERAS project slots specifically for IPPs, EPSA is concerned that unclear tariff language may inadvertently limit IPP participation in the remaining 58 projects. Moreover, MISO’s requirement that IPPs secure executed agreements with Load Serving Entities (LSEs) to qualify—unlike LSEs, which can rely on self-build options—places an undue burden on competitive suppliers. EPSA explained that power purchase agreements are typically secured only after advanced project development phases, making this requirement practically exclusionary.
- Call for Delay and Clarification: To ensure fair participation by IPPs, EPSA urged FERC to delay the ERAS application deadline for the ten IPP-designated slots. This extension would give all MISO states adequate time to establish verification processes and enable IPPs to finalize necessary commercial agreements.
- Concerns About Retail Choice Treatment: EPSA also flagged ambiguity in MISO’s approach to retail-choice states (Illinois and Michigan), where eight ERAS projects are set aside without the typical regulator verification requirements. EPSA requested that MISO clarify how “specific load” and “evidence of need” should be demonstrated in these markets, where competitive suppliers typically serve load through diversified portfolios rather than one-to-one resource matches.
Competition Essential to Energy Reliability
EPSA’s comments underscore the importance of preserving open access and competitive neutrality as regional grid operators develop expedited interconnection processes to address growing reliability needs. By advocating for greater transparency and nondiscriminatory practices, EPSA is working to ensure that all market participants have equitable opportunities to contribute new resources to the grid.
This approach will be crucial to maintaining reliability, promoting innovation, and driving cost-effective energy infrastructure deployment across U.S. power markets.