Date filed: December 5, 2025 | Venue: Federal Energy Regulatory Commission | Proceeding: Interconnection of Large Loads to the Interstate Transmission System, Docket RM26-4-000
“A reliance on innovative market-based mechanisms should be the foundation of any next step in this rulemaking proceeding, while plaintive calls to reregulate should be dismissed for what they are – self-serving mis-directions which will not help us achieve our national goals.”
Summary:
EPSA filed reply comments on the Department of Energy’s proposal (ANOPR) for FERC to create a standardized, expedited process for interconnecting large loads to the power grid.
EPSA addresses a few narrow issues raised in initial comments on the ANOPR, underscoring that pending proceedings with extensive existing records on co-location arrangements need guidance urgently from the Commission, suggesting a phased approach to establishing policies for large loads is appropriate and necessary.
Additionally, the reply comments rebut attacks on competitive power markets in an attempt to allow monopolistic behavior to flourish through state-led processes that allow transmission owners to build and rate base new generation in ISOs/RTOs.
EPSA also addresses comments that misread FPA Section 212(h) as limiting the Commission’s authority to act in this proceeding.
See EPSA’s initial comments on the proceeding here: EPSA Comments Support ANOPR to Speed Large Load Interconnections