A group of trade associations and generators ask FERC to stay proceeding on PJM Co-Location Tariff provisions and establish a 90-day settlement process to make needed progress on tariff support for co-located load arrangements
Date: April 22, 2025
Venue: Federal Energy Regulatory Commission
Proceeding: Show Cause Proceeding on PJM Co-Location Tariff Provisions, Docket EL25-49-000
On April 22, EPSA joined a coalition of parties in a motion urging FERC to issue a finding as expeditiously as possible that the PJM Tariff is unjust and unreasonable as it lacks provisions that accommodate co-located load and generation arrangements. The Joint Parties further ask that the Commission stay the Show Cause proceeding and appoint a settlement facilitator and/or settlement judge to actively engage, through publicly noticed settlement conferences, with PJM, the Transmission Owners, and any other interested intervenors in a concerted, focused, and good faith effort to resolve this proceeding within a 90-day period.
Comments on the answers submitted from PJM and the region’s Transmission Owners in this proceeding will be submitted tomorrow, April 23, but the Joint Parties have filed their motion early to underscore the need for an expedited, time-limited process to allow for the development of the tariff provisions needed to address co-location arrangements sufficiently and fully in the most expeditious manner possible.
The Joint Parties are: EPSA, the PJM Power Providers Group (P3), Calpine Corporation, Cogentrix Energy Power Management, Constellation Energy Generation, and LS Power Development.