Venue: Federal Energy Regulatory Commission
Date: August 22, 2024
Proceeding: ER24-2671-000
Summary: EPSA filed a limited protest and comments at FERC on CAISO’s Interconnection Queue Process Reform Proposal. EPSA opposed CAISO’s efforts to create a commercial interest scoring category but is generally supportive of CAISO’s other reform efforts.
On the commercial interest scoring category, EPSA argued CAISO’s proposal (1) violates open access principles, (2) could allow Load Serving Entities (LSE’s) to give preferential treatment to certain projects – including those that they are developing; and, (3) provides insufficient detail on how LSEs are to score and evaluate projects, which allows for a subjective and thus potentially discriminatory selection process that may not be focused on reliability or readiness.
EPSA asked that the Commission reject the commercial interest scoring category but approve the remainder of CAISO’s proposal as its other reforms would help to alleviate the backlog that exists in the ISO’s interconnection queue.