United States of America Before the Federal Energy Regulatory Commission
PJM Interconnection, L.L.C. } Docket Nos. ER19-1486-000, EL19-58-000
Answer of the Electric Power Supply Association and the PJM Power Providers Group to the PJM Interconnection, L.L.C. Extension Motion
The Electric Power Supply Association and the PJM Power Providers Group respectfully file this answer to the motion of PJM Interconnection, L.L.C. for a 30-day extension of time – until August 5, 2020 – to submit the forward-looking Energy and Ancillary Services Revenue Offset component of the compliance filing directed by the Commission’s May 21, 2020 order in these proceedings.
PJM also requests a shortened deadline of June 29, 2020, for all answers to the PJM Motion and requests that the Commission act by the last business day before the July 6, 2020, compliance deadline contemplated by the May 21 order.
PJM states that, even if the extension is granted, PJM will submit the remaining required elements of the compliance filing on July 6, 2020, as directed by the May 21 Order.