• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Electric Power Supply Association

  • Insights
  • Podcast
  • About EPSA
    • Policy Principles
    • EPSA Members
    • Our Staff
    • Careers
  • For Members
    • Join EPSA
    • Committees
  • Contact
  • FAQ
EPSA

EPSA

  • Newsroom
    • Media Contacts
    • Press Releases
    • PowerFacts
    • Factsheets and White Papers
    • Power Moves Newsletter
    • Opinion and Commentary
    • Social Media
    • Podcast
  • Policy & Advocacy
    • Policy Positions
    • Federal Energy Regulatory Commission
    • Federal
    • Judiciary
    • State
    • ISOs/RTOs
  • Power Facts
    • Rising Power Demand
    • Reliable Power
    • Energy Cost Savings
    • Environmental Progress
    • Energy Innovation
    • In Your State
  • Understanding Your Electric Bill
Home / PowerFacts / One Year Later, Ohio’s Energy Reform Is Driving Gigawatts of New Power and Storage

May 27, 2026

One Year Later, Ohio’s Energy Reform Is Driving Gigawatts of New Power and Storage

By EPSA

Prior to 2025, Ohio had zero BTM generation projects serving data centers or similar customers. Today, the Ohio Power Siting Board has permitted over 2 GWs of BTM projects, and another 2.5 GWs are pending. 

By Dylan Borchers, partner, Bricker Graydon Wyatt LLP 

The United States is entering a new era of electricity demand growth for the first time in decades. Data centers, advanced manufacturing, electrification, and industrial reshoring are driving unprecedented demand for reliable power and exposing the limitations of traditional infrastructure timelines. Increasingly, the states best positioned to compete economically will be the states capable of bringing new power online quickly. 

One year after the enactment of Ohio House Bill 15 (“HB 15”), the results are difficult to overstate. In just a single year, Ohio has gone from having virtually no large‑scale behind-the-meter (BTM) generation for data centers and industrial customers to hosting multiple gigawatts of new natural gas generation and battery storage. 

This wave of investment is not accidental. HB 15 fundamentally rewrote the rules for how large electric customers can self‑supply power in Ohio, while simultaneously accelerating the state’s permitting processes to match the pace of modern load growth. As a result, Ohio has emerged as a case study in how state‑level policy reform can translate directly into steel‑in‑the‑ground infrastructure. This success demonstrates that when paired with clear state policy frameworks, competitive markets can mobilize private capital quickly to meet rising demand. 

How HB 15 Changed the BTM Landscape 

Ohio law has long recognized the right of customers to self‑generate electricity. In practice, however, that right was constrained by ambiguity and legacy assumptions: generation generally had to be located on the customer’s “premises,” projects were typically limited to smaller renewable or cogeneration facilities, and anything even slightly novel risked being challenged as an unlawful public utility or an infringement on a utility’s exclusive service territory. 

HB 15 dismantled these constraints in three critical ways. 

First, the statute clarified that BTM generation may be owned or operated either by the customer or by a third party under leases, power purchase agreements, or other service contracts.  

Second, HB 15 expressly confirmed that qualifying BTM generation is not a “public utility” and does not violate certified service territories.  

Third, and perhaps most significantly, the law eliminated Ohio’s historic “same premises” requirement. Under HB 15, BTM generation no longer needs to be physically co‑located or adjacent to the customer’s load. Instead, the generation facility must simply be located on property controlled by the customer (such as through a lease), connected to the customer’s side of the meter, and deliver power using the project’s own wires rather than the utility’s distribution or transmission system.  

Customer‑Controlled Microgrids and Shared Systems 

HB 15 went further by creating a new statutory construct, referred to as the “mercantile customer self‑power system.” A mercantile customer self‑power system may include one or more generation facilities, battery storage resources, or both, so long as: 

  • The system produces electricity primarily for one or more large customers; 
  • Power is delivered directly to the customer side of the meter; and 
  • No utility‑owned wires are used. 

Crucially, the statute allows multiple large customers to participate in a single system. This feature opens the door to shared BTM microgrids serving industrial parks, logistics hubs, or clusters of data centers. It also allows systems to be built as portfolios, combining multiple generators, batteries, and fuel types to optimize reliability, cost, and sustainability outcomes. 

In practical terms, more complex configurations that were previously impossible are now moving forward. There is now active development work to interconnect islanded data center campuses and dedicated generation plants using 69‑kV and 138‑kV non‑utility lines, increasing redundancy and resilience. Before HB 15, such arrangements simply could not have been permitted under Ohio law. 

From Zero to Gigawatts in a Single Year 

The market response was immediate. Prior to 2025, Ohio had no BTM generation projects serving data centers or similar customers. Today, the Ohio Power Siting Board (OPSB) has permitted over 2 GWs of BTM projects, and another 2.5 GWs are pending at the OPSB. 

The permitting timelines tell an equally important story. Using existing accelerated OPSB review tracks and new regulatory “shot clocks,” projects that historically might have taken a year of more to permit have moved from application to approval in significantly less time. For example, Socrates South filed its OPSB application in March 2025, received approval in early June, and began construction shortly thereafter. The associated data center and BTM facility are expected to be operational by the end of 2026, which is years ahead of when new grid‑based capacity and transmission upgrades would realistically be available. 

Importantly, HB 15 does not lock generation into a permanent BTM silo. While the BTM arrangements enabled by HB 15 must serve customer load “primarily,” nothing in the statute prohibits those facilities from later transitioning into grid‑serving resources. Several projects have been explicitly designed as bridge assets: deployed quickly as BTM systems to enable near‑term load growth, with the option to enter the PJM interconnection queue and serve the broader grid once transmission upgrades are completed.  

A National Model Emerges 

One year in, Ohio’s experience with HB 15 offers a clear lesson: thoughtfully designed BTM frameworks can mobilize private capital at scale, deliver reliability benefits quickly, and complement—not undermine—the long‑term development of the bulk power system. 

For states grappling with data center growth, industrial reshoring, and persistent grid constraints, Ohio’s reforms provide a blueprint. By removing artificial proximity requirements, enabling shared customer systems, and pairing substantive policy change with expedited permitting, Ohio has turned what was once a theoretical concept into gigawatts of real‑world infrastructure. 

Dylan F. Borchers is a partner at Bricker Graydon Watts LLP, based in Columbus, Ohio. He has represented developers of more than 12,000 megawatts of new electricity generation capacity in Ohio and Kentucky, including natural gas combined‑cycle facilities, utility‑scale wind farms, utility‑scale solar projects, and battery energy storage systems. Dylan is actively engaged in the evolving behind‑the‑meter and distributed energy landscape, advising clients on emerging project structures and commercial models involving customer‑sited generation, co‑located storage, and on‑site energy solutions serving municipal, institutional, and commercial loads.   

Resources: 

  • H.B. 15, 136th Gen. Assemb., Reg. Sess. (Ohio 2026), available at Ohio Legislature – HB 15 PDF. 
  • Jenifer French, Chair, Pub. Utils. Comm’n of Ohio, Testimony Before the Ohio Senate Energy Comm. (Mar. 24, 2026), available at PUCO Chair French Senate Energy Testimony. 
  • Jenifer French, Chair, Pub. Utils. Comm’n of Ohio, Presentation Before the Ohio Senate Energy Comm. (Mar. 24, 2026), available at PUCO Chair French Senate Energy Presentation. 
  • Ohio Power Siting Bd., Natural Gas–Fired Power Plant Map and Statistics (Ohio Pub. Utils. Comm’n), available at Natural Gas Map and Stats. 

Read more:

EPSA Testimony in Support of Ohio House Bill 15 to Enhance Competition for Energy Growth
Ohio’s HB 15/SB2: A Model for Meeting Data Center Energy Needs Through Competition 
DeWine Signs Ohio Energy Reform, Sets National Benchmark for Competitive Power Markets to Meet Rising Demand 

Filed Under: Competitive Markets, Competitive Power Markets, Homepage Featured Article, Newsroom, PowerFacts, Reliability, Rising Power Demand, State Policy, Uncategorized Tagged With: affordability, Behind the meter, BTM, Competition, competitive markets, Data Centers, Demand, Electric Power Supply Association, energy policy, EPSA, load growth, microgrids, Ohio, Ohio HB 15, Ohio Legislature, Permitting Reform, power generation, power markets, reliability

Primary Sidebar

  • Media Contacts
  • Press Releases
  • Power Moves Newsletter
  • Factsheets and White Papers
  • Opinion and Commentary
  • Social Media
  • Podcast

Share

Home Page Help Area

Sign up for EPSA’s Power Moves newsletter – a monthly update on the road to a reliable energy future that works for all Americans.

LEARN MORE

Footer

1401 New York Ave. NW
Suite 950
Washington, DC 20005

p 202.628.8200
f 202.628.8260

  • Facebook
  • LinkedIn
  • Twitter
  • Home
  • About EPSA
  • Filings
  • Newsroom
  • For Members
  • Contact
  • PowerFacts
  • FAQ

Copyright © 2026