Backlogged queues for building new power generation pose a serious threat to the nation’s electric grid.

Connecting new resources to the grid through the interconnection queue is a time intensive and costly process that has failed to keep up with the rate of generation retirements and growth in electricity demand. The queue is the process by which power generation projects are approved to connect to the grid. During their time in the queue, projects undergo an interconnection study to assess their feasibility, impact on the power system, and costs to connect to the grid. It is vital to the stability of the grid that legitimate and fully financed projects get through this process quickly.
But right now, that’s not happening. New generators in many regions face years-long waits in backlogged interconnection queues, even while state and federal policies are pushing many older plants to retire prematurely. When existing dispatchable plants are retiring faster than new generation is coming online, that misalignment of resources marks the emergence of a serious threat to our nation’s electric grid.
According to the 2024 Advanced Energy United’s (AEU) Generation Interconnection Scorecard, interconnection customers across competitive market regions face huge uncertainty over the timing of the interconnection process, leading to additional costs and the withdrawal of many projects prior to reaching the end of the process. This also creates a problematic spiral where companies have an incentive to put as many projects into the queue as early as possible to maximize their odds, which increases review burdens for grid operators.
Although they were not addressed in the study, vertically integrated utilities in non-market regions are also struggling to connect resources to the grid. Regions without RTOs and ISOs, like the West and the Southeast, face some of the worst project backlogs in the country for renewable resources, according to Lawrence Berkeley National Laboratory.
Regional Variation and Cost (Un)Certainty
The AEU Scorecard confirms the widespread concern that the generator interconnection process is not working effectively and efficiently to allow new generation and storage resources access to the transmission network at a time when resource adequacy is of particular importance.
The problem dates back over a decade and there have been recent attempts to resolve this long-standing issue. FERC’s 2018 Order 845, for instance, acknowledged that “despite Commission efforts to improve the interconnection process, aspects of the generator interconnection process still provide cause for concern” — even as it issued reforms to promote more informed interconnection and enhance the interconnection process. In 2023, FERC would issue another interconnection rule, Order 2023, to address problems that stakeholders identified as causing severe interconnection delays and backlogs across the country.
Although it is too early to see how Order 2023 will impact the interconnection queue, the AEU Scorecard shows just how serious the problem remains. The Scorecard highlights deep concerns from interconnection customers about both high costs and cost uncertainty, and how the process is often prolonged past official timelines.
Table: Interconnection Process Results Grades
PJM was one of the lowest-rated regions in the Scorecard, with performance decreasing since the 2015-2017 cycle. Outside of ERCOT and CAISO, all regions suffered from a lack of cost clarity and long backlogs, but PJM was singled out as having the longest timeline and most uncertainty. AEU Scorecard’s findings reiterate PJM’s own Resource Retirements, Replacements and Risks report that warns 40 GW of power is at risk of retiring by the end of the decade and new generation may not come online because the historical rate of completion for renewable energy projects stands at 5%.
Managing Load Growth and Generation Retirements
The lack of a functional interconnection process is compounded by the growing need for new resources due to the electrification of the economy and state policies that are forcing dispatchable generation offline. Long interconnection queues and dismal completion rates for projects mean that many of the replacement resources will not be available in time to support the grid, if ever.
While the Scorecard notes that interconnected markets have made progress in addressing the issues in the interconnection process, the market needs to see these changes implemented sensibly and quickly in order to continue to deliver reliable and cost-effective energy to consumers.
Regional Spotlight
ERCOT
The Electric Reliability Council of Texas (ERCOT) was the highest rated interconnected market by AEU thanks to its simple and efficient processes that are moving projects through the queue in a timely manner. In discussing the assignment of system upgrades costs, the Scorecard found that interconnection customers in ERCOT pay very low interconnection costs, with projects’ current responsibility limited to certain direct costs of connecting the generator to the transmission system. The remaining costs are paid by the transmission provider, passed through to retail customers, and are widely predictable and consistently applied.
PJM
PJM Interconnection customers interviewed by AEU note that PJM’s interconnection study process for new projects has come to a full stop, with the hope that projects from 2019 may complete the process six years later in 2025. The Scorecard called the original serial process “sub-par” and singled out the policy of requiring limited financial commitments from participants until PJM was ready to offer an interconnection agreement. Because of this structure, projects would drop out very late in the process, causing a high number of restudies and resulting in inefficiencies and project delays.
As PJM’s interconnection capacity began to decline in 2017, it started to develop new practices to improve the processes that are being instituted today. The complete halt in approvals to allow the time to implement a better system hurt PJM’s scores, but the RTO hopes that new processes now in place will lead to lasting improvements.
The largest shift has been to a cluster study process that groups proposals on a ‘first-ready, first-served’ basis to help clear the backlog, and adoption of a “modeling enhancement” plan to revise its resource adequacy and capacity accreditation process. PJM will not accept new applications until 2025 and kicked off the first Transition Cycle of its reformed interconnection process on Jan 22, 2024, with 308 projects representing 46,000 MW of new, mostly renewable generation.
MISO
MISO identified the emerging gap between resources slowly connecting to the grid and resources retiring in its 2024 Reliability Imperative Report. According to their assessment, about 25 GW of approved resources are experiencing average delays of 650 days before commercial operation as of late 2023, with more expected.
To its credit, the Scorecard states that MISO is committed to transmission expansion and has made improvements to customer-facing and backend operational queue processes over the past several years to enable more efficient application processing. The Scorecard considers MISO’s interconnection process good, but inconsistent. However, MISO acknowledges that additional changes are needed to manage the dramatic growth in applications, and as a result, paused accepting interconnection applications for the 2023 cycle, with plans to resume in March 2024.
Market Reform Takeaways
As PJM and other regions reform the interconnection process, it is important that the modifications ensure a fair, just, and reasonable process that will enable expeditious interconnection and system reliability.
EPSA has offered comments to the Federal Regulatory Energy Commission about the need to facilitate the deployment and deliverability of all commercially viable projects to meet the challenges involved with decarbonizing the economy reliably.